ANNEX 1
IEA Technology Collaboration Programme on Tokamak Programmes (CTP TCP)
Annual Briefing 2020
1.
Preface
The objective of the CTP TCP is to
advance the physics and technologies related to toroidal plasmas. This is
achieved by strengthening cooperation among tokamak programmes, enhancing the
effectiveness and productivity of the research and development (R&D) effort
related to the tokamak fusion concept, contributing to and extending the
scientific and technology database of toroidal confinement concepts, and providing
a scientific and technological basis for the successful development of fusion
power.
In 2020, the Covid-19 pandemic had
a large impact on the international missions under the CTP TCP and there were
very few assignments completed. Therefore, a large support was given for
activities using remote participation tools and a lot of progress has been made
using alternative approaches. These included, the successful remote
participation in KSTAR (KO) experiments; the completion of the activities on
the shattered pellet injection on JET, remote participation on DIII-D (US),
EAST (CN) and KSTAR (KO) shattered pellet injection experiments, resonant
magnetic perturbation experiments in KSTAR (KO) and ECCD breakdown optimisation
experiments on DIII-D (US).
2.
ChairÕs report 2020
Membership
The participation of Thailand is
under discussion and observers from Thailand participated in the 10th
Meeting of the Executive Committee. The representatives from Thailand were informed
of the steps required for becoming members of the CTP TCP. However, in the
latest iteration with the representatives from Thailand in August 2020, it was
stated that the situation in Thailand has changed and that the process needed
to be restarted with the new ministry. The members of the CTP TCP Exco
unanimously agreed to wait for a clarification from Thailand regarding the
request to join the CTP TCP and not to vote on this issue at this meeting. The Chair added that once the situation
is clarified, the CTP TCP Exco would take a vote on this matter.
Regarding the invitation for Russia
to participate in the CTP TCP, Russia has been invited to the CTP TCP some
years ago and that efforts have been made to facilitate Russia joining the CTP TCP,
including sending letters written by the CTP TCP Chair to the Russian contacts
in at least 2 occasions. There have been iterations with contacts in the
Russian Ministries, but these efforts did not lead to a positive outcome.
Meetings
á
11th Executive Committee
Meeting ITER HQ, France, Thursday 10th December 2020
á
23rd meeting of the
International Tokamak Physics Activity Coordinating Committee (ITPA CC)
and
12th ITPA meeting for Joint Experiments ITER HQ, France, 8-9
December 2020
á
The Disruptions workshop usually
organised at Princeton was held via videoconference, in July 2020, under the
IAEA. This workshop focussed on Disruption mitigation. The agreement is to
continue to organise this meeting every year, alternating between the IAEA Disruptions
Workshop and the Princeton Theory Workshop.
á
The KSTAR conference, which usually
takes place in January or February, the date has not been agreed yet, but it
may take place in November or December 2021.
Communication
Three projects have been
submitted to IEA regarding the Today in the Lab - Tomorrow in Energy? Initiative
on: JET TAE Amplifier and Control Upgrade; Event Detection Intelligent Camera
(EDICAM) for the JT-60SA Tokamak and JET Shattered Pellet Injection for
Disruption Mitigation in ITER. The Event
Detection Intelligent Camera (EDICAM) for the JT-60SA Tokamak was published by
IEA. The Chair and Secretary participated in the TCP Chairs meeting on 8th
October 2020.
Status report
and milestones achieved
ITER
The ITER project continued to advance well in 2020 and a
crucial milestone was achieved on May 27 2020, with the 1,250-tonne
base of the cryostat successfully inserted into the Tokamak pit. This cryostat
base, 30 metres in diameter, was positioned with a final tolerance under 3 mm
at all metrology points. The cryostat lower cylinder was inserted on 31 August
2020 into the Tokamak Pit, fitting perfectly with the base. The delivery of the
second European Toroidal Field Coil took place on 4 September 2020. With the delivery
of the thermal shield sections from Korea, two toroidal field coils from Japan,
and the vacuum vessel sector 6 from Korea, the first sector pre-assembly will
start in 2021. Regarding the Poloidal Field Coils, Coil number 5 Winding Pack
assembly is almost completed, the Coil number 2 is in preparation for Winding
Pack impregnation, the Coil number 4 Double Pancakes winding has started; the Poloidal
Field Coil number 6 arrived in June 2020 and preparations for cold test are
almost completed. The fabrication of the Poloidal Field Coil number 1 in Russia
is well advanced. The ITER Research Plan previously released publicly as a ITER
Technical Report ITR-18-003 will be submitted to Nuclear Fusion in 2021. The
ITER Research Plan will be formally included in the technical baseline to
ensure consistency between hardware and research objectives in each phase.
Europe
Joint
European Torus (JET), Axisymmetric Divertor Experiment (ASDEX) Upgrade, Tokamak
ˆ Configuration Variable (TCV), Mega-Amp Spherical Tori (MAST) Upgrade, and
Tungsten (W) Environment in Steady-state Tokamak (WEST)
The delays caused by the COVID-19 Pandemic were mitigated by
remote scientific exploitation of JET and other European facilities. The first
plasma was achieved on MAST Upgrade on 27th October 2020 marking an important
milestone. MAST Upgrade is preparing to run initial physics experiments with over
3MW NBI power injected. The JET Shattered Pellet Injection experiments were
successfully completed; performing disruption mitigation at high energy and providing
unique data for ITER; with evidence that high-Z injection is not sufficient and
deuterium pellets found to be efficient in mitigating Runway Electrons. Promising
small ELM regimes for ITER and DEMO were found on TCV and ASDEX Upgrade with
good core performance, with high fuelling and reduced magnetic shear at the
plasma edge. The updated ITPA H-mode confinement database including the new
data from JET ITER-like Wall and ASDEX Upgrade W-wall concluded that the confinement
dependence on density and power degradation is weaker in metallic devices with
weaker dependence on density, major radius, and stronger dependence on the
plasma current with a projection to ITER predicting a 22% reduction in the
energy confinement time with respect to the previous scaling. The manufacturing
of the ITER-grade divertor components of the WEST Plasma Exhaust Upgrade has
been completed. The JT-60SA EUROfusion-F4E joint activities are progressing
well with the EDICAM wide-angle visible camera installed, 6 Enhancement
Projects on-going and a strong and coordinated EU
participation in the JT-60SA Integrated Commissioning.
Japan
JT-60SA
The assembly
of the upper part of the JT-60SA cryostat was completed; together with the
final positioning of the centre solenoid. The assembly of the top lid thermal
shield and the cryostat top lid was carried out and the assembling of the
tokamak was completed on March 2020. The check of the vacuum tightness, and
electrical ground and relative isolation for sub-assemblies has been carried
out. On September 2020, the pumping down of the vacuum vessel and the cryostat
started and both of them passed the leak tests. The cool down of the
superconducting coils and the thermal shields started on October 2020, and all
the superconducting coils have reached the superconducting state in November
2020. The coil energisation test will follow soon. After the coil energisation
test, operation with plasma can start. On the basis of the trilateral agreement
between the ITER organization (IO), F4E and QST, the information sharing on the
assembly and integrated commissioning is effectively on going with the IO.
China
Experimental
Advanced Superconducting Tokamak (EAST)
EAST long pulse high beta poloidal plasma operation in support
of the CFETR 1GW scenario was obtained with 3.5 MW of radio frequency Heating
and Current Drive in the tungsten upper divertor configuration, with improved energy
confinement time by increasing the density peaking factor. Divertor detachment studies
compatible with the grassy ELM regime considered in the CFETR design were
performed providing a robust solution to achieve long-pulse high-performance H-mode
operation with high heating power in a metal wall environment with several
feedback control schemes, but without the use of Resonant Magnetic
Perturbations as these are not foreseen for CFETR. Helium plasma experiments
were performed in support of the ITER operation and Plasma Surface Interaction
research. The upgrade of EAST is going on smoothly including new lower tungsten
divertor with new geometry, improvement of the capability of heating systems, position
rearrangement of heating and diagnostics with a new campaign planned from April
2021.
HL-2A
tokamak
New Capabilities in HL-2A include a new Hard-X ray camera and Supersonic
Molecular Beam Injection visualization. AlfvŽn Eigenmodes studies showed mode coupling generating multiple
modes, which can cause resonance overlap in real and phase spaces and enhance
transport and trigger avalanche events. Thresholds in terms of Electric Field
and velocity shear were determined for both L-I and I-H transition and the velocity
shear threshold was found independent of the plasma density and the total
heating power.
HL-2M
tokamak
SWIP has
completed the installation and assembly of the HL-2M tokamak with the mission to develop the physics basis for advanced plasma scenarios with
flexible divertors; to address burning plasma physics
issues and advanced tokamak scenarios in support of future machines.
Korea
Korean
Superconducting Tokamak Advanced Research (KSTAR)
In KSTAR, the
access to high qmin >2 high beta
scenarios has been expanded by early shaping, early
heating and H-mode transition controlled by power injection to avoid instabilities.
This strategy allows maintaining high qmin
showing strong dependency of confinement on qmin
and improved confinement with broader current profiles. Long pulses have been
sustained for 30 seconds in hybrid scenarios, however, the performance
gradually degraded mainly due to a drop in density and
ion temperature. High ion temperature discharges in diverted L-mode edge with
Upper Single node was sustained for 20 seconds in KSTAR with stable Internal
Transport Barrier. This was achieved with almost fully non-inductive current
drive with the loop voltage close to zero. ELM suppression was successful with
an adaptive controller searching for an optimal level of Resonant Magnetic
Perturbation. Two
identical Shattered Pellet Injection systems were installed in toroidally opposite locations in KSTAR in collaboration with
ITER-IO, ORNL, and KFE. Dual Shattered Pellet Injection experiments
demonstrated the feasibility of simultaneous multiple injection as planned for
ITER.
Spherical Torus at Seoul
National University (VEST)
Internal Reconnection Events in disruptions
studies found an experimental link between these ELM filaments and the
occurrence of Internal Reconnection Events, suggesting new mechanisms for the
interaction between the filaments and the internal modes that lead to the Internal
Reconnection Events onset.
United
States
Doublet
III D-shaped Tokamak (DIII-D)
DIII-D completed
the helicon antenna commissioning and started to conduct experiments. Three new
gyrotrons are planned to fill all available sockets.
In a planned vent of the vacuum vessel, in the latter half of year, a new lower
hybrid antenna will be installed.
National Spherical Torus Experiment
Upgrade (NSTX-U)
The
NSTX-U recovery project is proceeding with the delivery of six inner poloidal field
coils, with three spare coils being fabricated. The new centre stack casing is
now 80 % complete and first Plasma Facing component tiles have been delivered.
India
ADITYA-U
experiments in 2020 focussed on Runaways, Disruptions, MHD Modulations and
Plasma Rotation experiments. Disruption experiments showed faster current
quench times at higher edge q. Electromagnetic Pellet Injection experiments
showed that the current quench rate can be controlled by the amount of material injected.
Experiments on the effect of gas-puff on runaway electrons showed reduction of
the losses with suppression of edge fluctuations and it was shown that minor disruptions
triggered by Supersonic Molecular
Beam Injection causes runaway electron losses.
Steady
State Superconducting Tokamak (SST-1)
SST-1 is preparing for operations with the new superconducting
Poloidal Field coils later this year and no experimental campaigns took place
in 2020.
Future plans
Regarding the
personnel assignments, and remote participation 2021, there are still
uncertainties related to travel restrictions due to the covid-19 pandemic. However,
a strong effort is directed to the participation in the commissioning of
JT-60SA under the Broader Approach. The ITER-IO priorities relate to Shattered
Pellet Injection experiments on DIII-D (US), KSTAR (KO) and ASDEX-U (EU) and participation
on the JET experiments.