ANNEX 1
IEA Technology Collaboration Programme on Tokamak Programmes (CTP TCP)
Annual Briefing 2019
1.
Preface
The objective of the CTP TCP is to
advance the physics and technologies related to toroidal plasmas. This is
achieved by strengthening cooperation among tokamak programmes, enhancing the
effectiveness and productivity of the research and development (R&D) effort
related to the tokamak fusion concept, contributing to and extending the
scientific and technology database of toroidal confinement concepts, and providing
a scientific and technological basis for the successful development of fusion
power.
2.
ChairŐs report 2019
Membership
The participation of Thailand is
under discussion and observers from Thailand participated in the 10th
Meeting of the Executive Committee
Meetings
á
10th Executive Committee
Meeting ITER HQ, France, Thursday 12th December 2019
á
22nd meeting of the
International Tokamak Physics Activity Coordinating Committee (ITPA CC)
and
10th ITPA meeting for Joint Experiments ITER HQ, France, 10-12
December 2019
á
KSTAR Conference 20-22 February
2019, Coex, Seoul, Korea
á
PPPL Workshop on Theory and
Simulation of Disruptions Princeton Plasma Physics Laboratory, Princeton, New
Jersey 5-7 August 2019
Communication
Three projects have been
submitted to IEA regarding the Today in the Lab - Tomorrow in Energy? Initiative
on: JET TAE Amplifier and Control Upgrade; Event Detection Intelligent Camera
(EDICAM) for the JT-60SA Tokamak and JET Shattered Pellet Injection for
Disruption Mitigation in ITER.
Status report
and milestones achieved
ITER
The project continued to advance well in
2019 with 73% of construction (within First Plasma scope) completed on the
platform and 67% of total First Plasma scope achieved (design, manufacturing,
transport assembly). Impressive
progress has been made on the magnets, with two of the Toroidal Field coils
nearly complete (Japanese coil 12 and EU coil 9), the 17m diameter Poloidal
Field coil 5 in the final stages of completion in the on-site poloidal field
winding facility, and the first coil to be installed in the tokamak pit, PF
coil 6, complete and on the point of shipping from ASIPP in Hefei, China. The
cryostat lower cylinder is complete and awaiting installation, with the base
and upper cylinder in the final stages of assembly. In Korea, at Hyundai Heavy
Industries, the first sector (#6) of the nine sector, 20 m high vacuum vessel
is nearing completion and is expected on-site at ITER in the Spring of 2020.
The ITER Organization underwent a very significant reorganization in 2019, with
a new structure, better aligned to machine assembly and preparations for First Plasma,
to be in place by 1 January 2020. Inside that structure, the ITER Science
Division was reorganized to allow greater focus on First Plasma, preparations
for the early years of non-active operation and an intense effort towards
development of a disruption mitigation system based on shattered pellet
injection. This was accompanied by
a strong drive to provide a new focus for the International Tokamak Physics
Activity (ITPA), concentrating on R&D priorities for the ITER Research
Plan, completely revised in 2018 to be aligned with the new Staged Approach for
ITER operation. A great many of
these priorities are common to the efforts of the CTP-TCP programme
partners.
Europe
Joint European
Torus (JET), Axisymmetric Divertor Experiment (ASDEX) Upgrade, Tokamak
Configuration Variable (TCV), Mega-Amp Spherical Tori (MAST), and Tungsten (W)
Environment in Steady-state Tokamak (WEST)
JET Experiments have begun to explore the high-performance
domain at high power, where fusion power, impurity behaviour and MHD stability
will be optimised in preparation for the DT experiments. In these experiments an increase of
performance in the neon seeded scenarios was observed. An
ITER like tokamak agnostic control system was implemented on TCV and AUG and real-time
handling of the H-mode density limit disruption path was achieved on AUG and
TCV with the discharge trajectory followed in real-time in confinement and edge
density space. Central heating was applied if the discharge approaches the unstable
area and with similar stability boundary
on AUG and TCV. Small Edge Localised Mode scenarios on AUG and TCV have shown
the importance of magnetic shear at the magnetic separatrix and it was shown
that the baffled TCV divertor increases the divertor neutral pressure and
extends the detached regime, confirming model predictions. Experiments with the
Shattered Pellet Injector on JET for ITER were carried out after successful
commissioning of the system developed in collaboration with US and ITER.
Deuterium, Neon and Argon pellets as well as Deuterium and Neon and Deuterium
and Argon mixtures were used with all three barrels. Run-away electron beam
suppression with shattered pellet was demonstrated and unexpected results were
obtained with 12mm Deuterium pellets leading to suppression of fast electrons. More
than 4 weeks of Helium plasmas were executed in the WEST tokamak equivalent to 2000
seconds of Helium plasma exposure and a fluence of 2.5 1025 He/m2.
Japan
Japan
Torus 60SA
The fabrication
of most of the key components has been finished. Assembly of JT-60SA is
approaching the final stage towards its completion and the start of the
integrated commissioning and the first plasma is foreseen in 2020. Assembly of
the lower part of the cryostat has been finished. Thermal shields have also
been assembled. Preparation and test of subsystems, power supplies, vacuum
systems, cryogenic systems, heating systems, diagnostics, are proceeding
towards completion. Work procedure documents of the integrated commissioning
for each subsystem and plasma operation have been established. Lively
discussion between Japanese and European physicists have been on going. The 8th
Research Coordination Meeting (RCM-8) was held at QST Naka on 24 - 26 June
2019, in which about 60 experts participated including a representative from ITER,
for the discussion on the research items on JT-60SA.
China
Experimental
Advanced Superconducting Tokamak (EAST)
Fully
non-inductive operation, steady-state scenarios using pure Radio Frequency
heating have been developed in EAST as well as steady-state grassy Edge
Localised Mode regimes and steady-state scenarios with detachment feedback
control. Other techniques to control Edge Localised Modes included suppression
by Boron Injection without confinement degradation and Resonant Magnetic
perturbations in ITER relevant low safety factor - type I Edge Localised Modes
regime.
HL-2A
tokamak
The mission of
2019 HL-2A experimental campaign addressed critical physics and technology
issues in high beta and H-mode plasma scenarios. Plasmas with _N>3
operation have been achieved with high Neutral Beam Injection and Radio Frequency
power for the first time. Type I Edge Localised Modes mitigation and control
have been achieved by mixture of Super Molecular Beam Injection, Resonant Magnetic
Perturbations and Lower Hybrid Waves.
In the low central magnetic shear configuration, fishbones plays an
important role in the formation and sustainment of Internal Transport Barriers.
It was observed that turbulence and turbulence spreading across the magnetic
island are modulated by the rotation of tearing modes. Partial detachment was
achieved in H-mode plasmas with Neon gas seeding.
HL-2M
tokamak
The mission of
the HL-2M tokamak, under construction by the Southwestern Institute of Physics
(SWIP), is to develop the physics basis for advanced plasma scenarios with 3MA
plasma current, high beta (_N > 3), high elongation (_ = 1.8-2),
high triangularity (_ > 0.5), and snowflake divertor in support of future
fusion machines (ITER, CFETR). The goal is to have the first plasma in May
2020. A several-stage development plan for the heating, control and diagnostic
systems has been formulated. The physics of high confinement scenarios,
advanced divertor configuration, heat and particle exhaust physics through
active control of instabilities and disruption will be studied in detail.
Korea
Korean
Superconducting Tokamak Advanced Research (KSTAR)
In KSTAR, important steps for
advanced scenario development have been achieved with early divertor
configuration access, high safety factor and high internal inductance.
Long-pulse hybrid scenarios were explored in pulses of up to 9 seconds and
double null plasmas were studied with significant increase in the stored
energy. Disruption prediction and avoidance research on KSTAR is moving towards
real-time applications. Nonlinear
MHD modelling has reproduced the key elements of the Edge Localised Mode
suppression observed by Electron Cyclotron Emission imaging. The measured
electron temperature profile corrugation has been reproduced in Gyro-kinetic modelling,
where the Zonal Flow staircase is the key mechanism. Dual Shattered Pellet Injector experiments have been performed
with the two injectors in opposite sides of the tokamak allowing the studying
of disruption speed dependence on impurity contents and radiation
efficiency using a high-speed camera.
Spherical Torus at Seoul
National University (VEST)
Plasma
currents up to 170 kA have been achieved in VEST and an accelerated rotation in
the opposite direction of the plasma current has been observed after strong ion
heating during an Internal Reconnection event.
United States
Doublet
III D-shaped Tokamak (DIII-D)
DIII-D successfully
completed 12 run weeks in 2019 following the installation of worldŐs first
toroidally steerable, off-axis neutral beam injector and demonstrated the
top-launch electron cyclotron current drive system which works as intended. The
helicon antenna modules have been fabricated and the design of the high-field-side
lower hybrid system has been completed.
National Spherical Torus Experiment
Upgrade (NSTX-U)
The NSTX-U Recovery Project is ongoing.
Key project elements include replacement of the six inner-Poloidal Field
magnets, numerous improvements to the structural and vacuum properties of the
vacuum boundary, improve high heat flux plasma facing components, improvements
to the test cell shielding, a new test cell access control system. The Project
has a DOE-approved cost and schedule, having completed a successful Integrated
Project Review in August 2019. The design phase of the Project is near
complete, with the last Final Design Reviews to occur in the winter of 2020.
Numerous components are under fabrication as approved long-lead procurements.
These include six new inner-Poloidal Field magnets, as well as a new centre-stack
casing; these are the two largest single fabrication activities on the Project.
Improvements to the test cell nuclear shielding are in progress. All other
major procurements and fabrication will be completed in 2020. The Machine
reassembly is scheduled to commence in the summer of 2020. The early-finish
date for the Project, followed by the resumption of operations, is May 2021.
Preparations are underway to re-establish the Research Team and Program.
India
ADITYA-UG
The ADITYA-UG tokamak
achieved 177 kA of plasma current at the maximum toroidal field of 1.4T. The
plasma pulse duration was extended to 335 milliseconds in 2019. Experiments
with an Electromagnetic Pellet Injector have been performed and 200mg pellet of
Lithium Titanate particles were injected during the plasma
current flat-top. Pellet injection causes the fast disruption of the plasma
current density. The temperature reduces
very rapidly due to increased plasma radiation after the injection. Significant suppression of Runaway
Electron Loss was achieved by suppression of edge density and potential
fluctuations using periodic gas puffs.
Steady
State Superconducting Tokamak (SST-1)
Two experimental campaigns were carried out in SST-1
in 2019 performing ECRH assisted Ohmic breakdown studies and lower hybrid
current drive experiments. Several technical issues related to cryogenic heat
loads has been resolved with the Toroidal Field coils tested to the highest
ever field of 2.7 T. Multiple gas puffs showed to suppress hard X-rays
generated in low density discharges and recent lower hybrid current drive
experiments showed significant improvement in the control of the operating
pressure, resulting in the improved efficiency of Lower Hybrid Current Drive.
Future plans
Europe: Key
Enhancements for the scientific exploitation in support to ITER are being
planned for JET, including a second
shattered pellet injector and associated diagnostics and a ITER relevant Laser
Induced Desorption Spectroscopy. The participation in the JT-60SA Integrated
Commissioning and first plasma operation is being prepared with the nomination
of the EUROfusion on-site coordinator and deputies.
Korea: KSTAR
upgrades includes a plan for higher beta and steady-state operation with the
installation of an actively cooled Tungsten Divertor and advanced current drive
systems. These include the installation of a Helicon Advanced Current Drive
System aiming at demonstrating a 0.15 Amperes / Watt of current drive with the
injection of 4 MW of auxiliary power.
United States: The
2020 DIII-D program is focused on utilising several Heating and Current drive
systems in steady-state scenarios and the installation of the helicon antenna.
The NSTX recovery project is aiming at the completion date of July 2022.
China: In
2020 EAST aims at long-pulse H-mode operation for longer than 400 seconds in a
full metal wall environment, in scenarios relevant to CFETR and in support of
ITER physics.
The
new tokamak under construction at SWIP, HL-2M tokamak, will have the first
plasma in 2020. HL-2A tokamak at SWIP also plans to operate end of 2020, and
the experimental compaign will continue into the Spring of 2021.