IEA
Technology Collaboration Programmes for
Co-Operation
on Tokamak Programmes (TCP-CTP)
Short
annual brief to the Fusion Power Co-ordinating Committee
Anual Briefing 2018
1.
Preface
The objective of this agreement is
to advance the physics and technologies related to toroidal plasmas by
strengthening cooperation among tokamak programmes, to enhance the
effectiveness and productivity of the research and development effort related
to the development of the tokamak fusion concept, to contribute to and extend the
scientific and technology database of toroidal confinement concepts, and to
provide a scientific and technological basis for the successful development of
fusion power.
2.
ChairŐs report
The change of the Japanese Contracting
Party to "QST Japan" has been finalised.
The Participation of AustraliaŐs
Nuclear Science and Technology Organisation (ANSTO) as a Contracting Party in
the CTP IA became effective as of 7 June 2018.
Meetings related to the
TCP-CTP included the 9th Executive
Committee Meeting of the IEA Technology Collaboration Programmes for
Co-Operation on Tokamak Programmes (TCP-CTP), Thursday 17 January 2019, ITER
Headquarters, France; 9th International Tokamak Physics Activities (ITPA) Joint
Experiments Workshop (JEX), 15-16 January 2019, ITER Council Room, ITER
Headquarters, France; 19th Meeting of the ITPA Coordinating
Committee, CTP-ITPA JEX Planning Meeting, 15-16 January 2019, ITER Council
Room, ITER Headquarters 72/5010, France; KSTAR Conference 2018 21-23 February,
2018 and PPPL Workshop on Theory and Simulation of Disruptions 16-18 July 2018.
The Website http://ctp.jet.efda.org/tcp/ has been significantly upgraded, modernised and the information revised.
Status report and Milestones achieved
ITER Tokamak: ITER construction continues
to advance at pace and moving forward towards the start of the assembly phase.
Construction and manufacturing is on track for first plasma in 2025, with the 60%
construction completion milestone reached at the end of 2018 and the bioshield
finalized. The latest update of the
ITER Research Plan was published on 17 September 2018. A wide-ranging physics
R&D programme, covered in many cases by the TCP-CTP, is addressing key
issues impacting on the finalization of the ITER design and preparations for
operation and it is important to maintain or even increase the commitment as
ITER prepares for plasma operation.
EU Tokamaks
(JET, ASDEX-Upgrade, TCV, MAST, WEST):
In order to
keep the timeline inside 2020, it is necessary to reduce the JET experimental
scope and priority has been given to experiments with the new JET Shattered
Pellet Injector and to DT operation. Euratom, the ITER Organization and the US
Department of Energy are collaborating on the test of the Shattered Pellet
Injector at JET. The system is now
installed and commissioning is underway.
First pellets have been formed but not yet injected into JET plasmas. Following some remedial work on the
cryogenic subsystem, the present plan is to complete commissioning this spring
with experiments planned for the summer of 2019. The AUG programme was delayed
due to repair work leading to the start of the campaign in November 2018 and
operation will continue until end July 2019. In TCV, the majority of the
programme was executed despite small issues with the upper internal
vertical-stabilisation coil and one of the X2 gyrotron prevented to complete some
experiments. For MAST-U the construction phase was completed in 18th
October 2018 and first plasma is foreseen for 2019. Good progress in WEST
operation, with up to 5.5MW of injected power and 37 second pulse was achieved.
The WEST tokamak was controlled from the Remote Experiment centre in Japan on 28th
November 2018.
JT-60SA
Tokamak (Japan): Fabrication and installation of
components and systems of JT-60SA procured by EU and Japan are steadily
progressing towards start of operation in April 2020 and the first plasma in
September 2020. Up to Nov. 2018, all the 18 Toroidal Field coils, 6 Equilibrium
Field Coils and 360-degree of the Vacuum Vessel have been assembled on schedule
with sufficient accuracy. Manufacture of all the 4 Central Solenoid modules
have been completed. Commissioning of the Superconducting Coil Power Supply
integrating EU and JA procurements have been completed. The 7th Research
Coordination Meeting (RCM-7) was held at QST Naka on 4-8 June 2018, in which 60
experts participated including a representative from ITER. Update of the
JT-60SA Research Plan to Ver.4.0 (SARPv4.0) was completed in September 2018
with 435 co-authors.
EAST Tokamak
(China) significant extension of the operational
regime towards steady-state operation for ITER and CFETR was achieved,
including long pulse steady-state H-mode operation with upper tungsten divertor
achieved with integrated plasma control, saturated W-Divertor surface
temperature after 10 seconds, good confinement and small ELMs. Recent
experiments extended the steady-state high beta poloidal scenarios using Radio Frequency
Heating and Current Drive only; and achieved 50% of bootstrap current using
combined Neutral beam and Radio Frequency Heating and Current Drive.
HL-2A Tokamak
(China) achieved Detachment during H-mode
with the Gas pressure in the divertor increasing significantly without any
change in the main chamber pressure; due to high compression and high pumping efficiency.
ELM mitigation was studied using Lower Hybrid Current drive, laser Blow-Off and
Super Molecular Beam and Pellet injection. ELM mitigation with LHCD led to
significant reduction of the divertor heat load.
KSTAR (South
Korea): Significant progress has been
made in discharge development, including the development of a double Internal
and External Transport Barriers triggered by turning off Electron Cyclotron
Heating. Internal Transport Barriers were achieved at a magnetic field of 2.5 T
in a discharge that lasted 20 seconds. A new record pulse length was achieved
in KSTAR with Water-Cooled Plasma Facing Components. A Grassy-ELM Steady-State
Hybrid Regime was produced with 3D fields. Significant progress on physics
understanding of Resonant Magnetic Perturbations suppression of ELMs was achieved
with divertor peak heat-flux and n=2 mode-locking control with 3D fields. An impurity
powder dropper has been installed on KSTAR under the collaboration between NFRI
and PPPL/DIII-D. The essential role of fast ions and Alfven Eigenmodes were
identified on global confinement High-beta discharges. Stability, transport,
and active MHD mode control analysis have been used on KSTAR high performance
plasmas in support of disruption avoidance. The kink plasma response was
measured using rotating Resonant Magnetic Perturbations.
DIII-D (US)
has initiated over $20M of enhancements and infrastructure improvements as a user
facility to maintain and advance its world-leading research capabilities and NSTX
(US) has accelerated the recovery efforts.
ADITYA Tokamak
(India) dismantled in 2015 and ADITYA-U reassembled in 2016 with new circular vacuum
vessel, possibility of open divertor operations, and focus on Disruptions, Runaways
and other MHD studies. Operational control over Runaway Electron content in
ADITYA-U lead to Discharges with and without Runaways, the study of sawteeth generated Runaways and their transport and
mitigation by Super Molecular Beam Injection. Reversal of carbon ion toroidal
rotation in discharges with high density and Multiple Harmonics of
Drift-Tearing Modes were studied.
SST-1 Tokamak
(India) was mostly non-operational in 2018 due to technical issues in the Poloidal
Field coil cooling.
Future
plans
Europe has
issued a revised roadmap to the realisation of fusion energy aiming at
demonstrating fusion electricity early in the second half of the century, based
on a number of technical assessment reports. The Roadmap, provides a coherent EU
programme with a clear objective and avoids open-ended R&D. Various devices
(ASDEX-Upgrade, MAST-Upgrade and TCV) are upgraded to accommodate plasma
exhaust studies.
KSTAR (South Korea) upgrades
are ongoing aiming at achieving 28 MW Heating and Current Drive with steady-state
operation capability.
DIII-D (US) research
plan is aimed at advancing the world towards fusion energy, focussing on critical
ITER preparation, transients and development of validated simulation capability
and developing a basis for tokamak path beyond ITER with high performance core
and compatible boundary solution. Major ongoing tasks include: new co/counter
off-axis neutral beam modification, the WorldŐs first top-launch ECCD
capability; installation of helicon strip-line antenna and new and upgraded
diagnostics.
In EAST (China) a
new W lower divertor upgrade is scheduled in 2019, which includes Simple flat
targets to reduce installation error and thus leading edges, a closed outer
divertor and open inner divertor for balanced detachment and a water-cooled
internal coil for X-divertor operation.
Engineering Test Reactor (CFETR),
China: New Program for CFETR supported
by MOST includes, overall design, overall project management and standardisation,
Heating and Current Drive, Diagnostics and CODAC, Cryogenics, Vacuum Vessel,
pumping system Cryostat and thermal shield, In-vessel components, power
supplies, water cooling, remote handling assembly and maintenance, fuel
recycling and disposal, radioprotection and safety.